Case Studies > Urban
Railway System
Location Confidential
An urban railway system inclusive various systems such as the rolling stock,
trackwork, switches, contact rail, traction power and power distribution, operations
and control systems, in addition to building and civils installations such
as the guideway and platforms, stations, parking, tunnels, equipment rooms,
maintenance and storage facilities as well as a central control room and administrative
offices. The contract was awarded by a government agency (the Employer) to
a number of main contractors of which our client was one (the Contractor).
KEY FEATURES
A fixed price, lump sum, turnkey contract let under
the Employer's hybrid form of design and build contract with the Employer
and the Contractor as the only parties to the contract, there being no
administrative agent or "Engineer" as found under several well
recognized international standard forms of contract.
The contract involved complex contractual interfaces
with eight other main contractors coordinated overall by the government
agency in addition to numerous technical interfaces with several key
subcontractors across a broad series of buildings, civil works and hi
tech systems installations. A high level of overall project coordination
and control was requird to uphold the time and cost constraints under
the terms of the contract.
Due to numerous causal events of disruption, delay,
additional cost and expense, during the design, procurement and construction
phases of the project, as well as due to contract variation orders, both
the contract time for completion and the original contract price were
considerably exceeded. The government authority had previously awarded
several contract variation orders, extensions of time and monetary claims
for additional costs, loss and expense during the first few years of
the contract period. Moreover, an additional agreement document had been
drawn up, formalized to record all the approved and agreed changes and
the conditions under which the works affected by the changes were to
be executed.
Our clients were of the opinion that further contractual
entitlements to both extensions of time and financial reimbursement had
arisen out of ongoing disruptions, critical delays, contract prolongation
and other events causing loss and expense occasioned by the Employer
and/or other contractors. In addition to such claims, our client also
considered proposals for acceleration measures to the "works to
complete" as being in the best commercial interest of the Employer.
CONSULTANCY SERVICES
Lancaster House International Consulting were requested
to mobilize rapidly to our client's project offices, initially review
the key contract documentation together with preliminary contractual
claim submissions and commercial proposals for a re-sequenced and accelerated
completion of the remaining works. Our client's staff had prepared their
drafts in conjunction with a firm of American construction lawyers. Our
commission included determining what breaches of contract had occurred,
causing both time and cost overruns and identifying which party(ies)
was/were responsible; providing advice on where there may be opportunities
for improving the likelihood of the submissions being readily appreciated
by the Employer and the appropriate level of compensation being awarded.
It was imperative that the submissions were prepared and handled in a
manner that would not cause a deterioration of project relationships
and lead the parties into dispute. We worked closely with our clients
and their lawyers in obtaining a factual background and, setting this
information against the provisions of the contract documentation, we
were able to make clear recommendations for improvements in the format
and content of the claims and commercial proposals to meet the terms
of our brief. Our conclusions were submitted under an executive summary
report for consideration by our client's senior managment and the lawyers
and thereupon actions were taken accordingly. Our involvement produced
a substantially positive outcome. |