Case Studies > Urban
Heavy Rail and Tram System
Location Confidential
The entire design, supply, installation and maintenance
of a complete urban heavy rail system including the track work, switchgear,
power systems, control systems, tunnels, building and civil works, signalling,
stations, and rolling stock. The contract was awarded by a European government
agency for transportation (the Employer) to a design and build consortium
of which our Client was the lead consortium member.
KEY FEATURES
The contract was awarded on a fixed-price, lump-sum
turnkey basis under the Employer’s hybrid form of design & build
contract. Our Client considered that the general conditions of contract
contained a number of serious potential commercial risks vis-à-vis
the Employer and vis-à-vis their civil works consortium partner.
They concluded that they needed to ensure that the potential materialization
of such risks was minimized and those that did materialize needed to
be managed effectively and where possible obtain compensation. The contract
was also subject also to the jurisdiction of a complex legal system.
A number of post contract events had occurred which was causing serious
slippage to the contract programme and a significant overrun to the project
budget.
CONSULTANCY SERVICES -
Commercial and Contractual Management & Administration
Claims Management
Lancaster House International Consulting were asked
to undertake the role of consultant commercial and contractual administrators
and claims managers. Our primary functions required that we were based
on site for a period of two years, working as an integrated member of
the project management team. We reported on a daily basis to the Site
Project Manager and Site Commercial Manager with regular support from
our Düsseldorf office on complex contractual issues.
One of our initial tasks was to undertake a complete
review of the main contract terms and conditions together with associated
documentation, including the consortium agreement. The purpose of this
review was to identify what financial / commercial / contractual risks
currently existed or might arise, under which circumstances they had
or might manifest themselves and what the real or potential consequences
would / might be. [A Technical Risk Analysis had already been completed
by our Client to which we had access]. We were then required to make
recommendations for the effective control of those risks which had already
and may very likely in future materialize and consequently we produced
a strategy report covering events under the contract programme for completion,
the contract price, payment provisions, contract variations, penalty
provisions for breach of contract, warranties, and administrative matters
in relation to claim handling and dispute resolution procedures. Various
tools and procedures for the management of the various risks areas we
determined were developed by us and integrated within the Client’s
PM systems. We performed the day to day commercial and contractual administration
of the main contract and the consortium agreement both towards the Employer
and vis-à-vis our Client’s consortium partners which included
the drafting and vetting of all project correspondence, progress reporting
and contributed to the preparation of financial forecasts. We also carried
out the administration of several key subcontracts and researched and
prepared the contractual and financial bases for contract V.O.’s
and claims.
Part of the added value we delivered included a local
knowledge of the business culture aligned to our experience in the international
rail industry and associated civils works.
Our close liaison with the Client’s Project Manager
and his team as well as with internal and external teams of lawyers in
connection with the interpretation of complex substantive legal issues,
contributed to the successful application for extensions of time to various
sectional completion dates through the demonstration of Employer caused
or responsible delays. We were also instrumental in the award of substantial
variation orders, dayworks orders and contractual claims for the reimbursement
for additional cost and loss and expense. Ultimately, our Client recovered
control of the project and with it its financial position was restored
in line with original budget estimates. |