Case Studies > Residential
Development/Shopping Centre
Location Confidential
A high-rise mixed development of residential apartments
and a shopping centre, comprising building and civil works, mechanical
and electrical installations, instrumentation and control systems. The
contract for the mechanical and electrical works was awarded by a private
developer (the Employer) to a Consortium (the Contractor) of which our
Client was the Consortium member responsible for the supply and installation
of the mechanical works. The Employer retained responsibility for both
the basic and detailed design and engineering of the high-rise development
as well as for overall coordination and project management.
KEY FEATURES
The contract for the mechanical works was awarded on a fixed-price, lump-sum
basis under the Employer’s hybrid form of FIDIC „Yellow Book“ and
was subject to numerous causes of disruption, delay and additional cost and
expense during the various phases of procurement and construction. Primarily,
this was resultant from a number of key Employer initiated design changes and
the ripple effect through several interfaces with other executing contractors.
Serious delays occurred to the Contract date for completion as a result thereof
and which subsequently exposed our Client to the potential liability for damages
for delay. The Employer had furthermore failed to recognise our Clients entitlement
to the reimbursement of bona-fide contract variations to the works instigated
by its agent responsible for the basic and detailed design, nor take into account
the impact such contract variations might have upon the contract date for completion.
CONSULTANCY SERVICES - Claims Management (Prosecution
/ Defence)
Lancaster House International Consulting were requested to undertake a fully
detailed review and analysis of the historical events and circumstances which
had given rise to the contract prolongation and cost overruns. Our terms of
reference included the establishment of the Employer’s liability (if
and where possible), for the various causal events of disruption an delays,
sufficient to demonstrate an entitlement to an extension of time to the contract
date for completion for or beyond the overall period of delay, thus removing
any liability for liquidated damages for delay, sufficient also to establish
entitlement to financial compensation for all prolongation costs incurred as
well as any other identifiable items of loss and expense incurred. Our Client
also requested that we completely review and, as necessary, redraft the numerous
contract variation orders notices submitted by them to the Employer
Due to the complexity of the contract, the substantial
potential liability and timeous urgency in order to preserve our Client’s
rights and avoid the impending deduction of damages, we immediately mobilized
a team of bilingual (English / German) claims consultants experienced
in this type of project. We commenced with a complete review of the project
historical record, the entire set of contract documents, (not only those
relating to our Client’s scope of works), as well as all correspondence
between the Employer and other Consortium members. We conducted several
interviews with key personnel in the Client organization and analyzed
a breakdown of all variations to the project works, (both those recognized
as such and those not), and thereafter prepared a prognosis of the net
resultant effect upon our Client’s contract programme for completion
of its scope of works.
We subsequently concluded that the Employer was solely
and entirely responsible for the critical delays to the mechanical works
contract and prepared a fully substantiated and detailed statement of
claim for an extension to the date for completion of the mechanical works.
Furthermore, we redrafted the contract variation order requests previously
prepared by our Clients while at the same time prepared a considerable
number of new variation order requests which had previously not been
identified. Our Client discovered that much of the additional costs,
loss and expense which it had suffered could be recovered not only through
the demonstration of prolongation costs, but also through the proper
application of the contract provisions relating to variations of the
works and the correct means for their evaluation and measurement.
Our Client was subsequently awarded the requisite extension
of time, avoided the application of damages for delay in entirety and
received reimbursement in full for the additional cost and expense incurred
as a result of the extended contract period. After conclusion of these
claims negotiations, we were also successful in obtaining full reimbursement
of the revised submission of the contract variations to the works. The
awarded extension of time together with the level of financial recovery
achieved meant we were able to radically turn around the while commercial
basis of our Clients project. |