Case Studies > Power
Station
Location Confidential
A desulphurisation plant to an existing power station
(gas and natural fossil fuel), comprising all mechanical and electrical
engineering installations, power and power distribution, operations instrumentation
and control systems together with all associated building and civil works.
Our Client was one of the tenderers selected by the local government
agency for power (the Employer) for final negotiations of an agreed contract.
KEY FEATURES
The contract was to be awarded on a fixed-price, lump-sum, turnkey basis using
the Employer’s standard form of design and build contract. The contract
programme required our Client in erecting, installing, commissioning and testing
the entire desulphurisation plant during the period when the power station
was operational and without interruption to power supplies. This involved numerous
complex technical and resultant contractual interfaces. In addition, the form
of contract and the general conditions posed a number of exceptionally high
levels commercial risk in the opinion of our client and provisions for such
eventualities had to be made without jeopardizing the negotiations towards
a successful bid.
CONSULTANCY SERVICES – Commercial and Contractual
Risk Analysis
Lancaster House International Consulting were requested by our Client to undertake
a commercial and contractual risk analysis in respect of the “Head Contract",
to identify and highlight categories and areas of risk with a prognosis of
potentiality and “what if” scenarios. Simultaneously, we were required
to draft provisions under a set of “Special Conditions of Contract” for
negotiation with the Employer as considered necessary, in our opinion, to mitigate
and otherwise mange the said risks together with providing our Comments & Recommendations
on risk pricing and risk management . The initial contract appraisal and risk
analysis comprised a detailed examination of the Instructions to Tenderers,
other bid documentation issued by the Employer, the General Terms and Conditions
of Contract, specifications and drawings. We looked into risk types emanating
from technical, commercial and contractual sources and from this, we identified,
for example, several major potential commercial risk items through important
omissions within contractual terms and conditions. Certain provisions as drafted
in the tender documents were wholly inappropriate to the nature of the project
and the objectives of both the Employer and Contractor. Examples of such poor
drafting were the limiting effect upon the Employer’s rights to issue
variation orders, the Contractor’s entitlement to obtain an extension
of time for delay, and the reimbursement of prolongation costs and other additional
costs arising therefrom. A detailed subject matrix of risk exposure under the
provisions of the Head Contract was also drafted with corresponding recommendations.
In order to classify the seriousness of the risk a
simple classification by categories was adopted namely:-
Category 1: Serious Risks (A - Technical / B - Commercial
/ C - Contractual)
Strenuous efforts to achieve acceptance of suitably amended wording of the
offending article, clause, provision to eliminate the risk(s) in entirety.
Category 2: Significant Risk (A - Technical / B - Commercial
/ C - Contractual)
Conditions of Contract wording to be amended if possible during negotiation
(through clarifications and qualifications) and where possible transferred
to the Employer or others. Otherwise, such risks to be monitored and managed.
Category 3: Allowable Risk to be allowed for (priced)
within the Tender Submission.
Category 4: Low Risk Issues to be monitored and controlled
Special Conditions of Contract were drafted by us to
eliminate the identified Serious Risks and we were successful in assisting
our Client in negotiating with the Employer to obtain the entire elimination
or transfer of such risks to the Employer.
Finally, Lancaster House International Consulting provided
further recommendations to minimise the risk by way of effective documentation
and tracking of same, project records, the early identification of entitlement,
and prompt notification, including close relations between technical
/ commercial / contractual corporate divisions and the rapid conversion
of entitlement into quantified and reimbursed claims. |