Case Studies > Off-gas
Project
Location Confidential
A BP Chemicals DF Off-gas Project with Waste Heat Boilers
to a Thermox Plant, comprising of all mechanical and electrical engineering
installations, waste heat boilers, steel structures, piping, power and
power distribution, operations and control systems. The project structure
was arranged such that a Managing Contractor acted as the Employer with
overall responsibility for the entire Thermox Plant works within a turnkey
framework and therefrom, awarded a design and build contract to a Consortium
of specialist firms acting as the General Contractor. Within that Consortium,
our Client acted as consortium leader responsible for overall coordination
of the member firms and for representation and direct interfacing with
the Employer. However, their physical scope of work was limited to the
basic and detailed design for the waste heat boilers and associated works
(defined within a so called “Black Box” scope of work), including
all appurtenant structural steelwork and pipework.
KEY FEATURES
The Consortium contract (for the design & build scope), was awarded on
a fixed-price, lump-sum basis under the Employer’s standard form of contract.
Shortly after this contract came into effect, it was subject to numerous causes
of disruption and delay as well as considerable additional costs, loss and
expense. The multifarious causal events giving rise to such consequences occurred
throughout the various project phases to varying degrees to create a myriad
of complex interdependent cause and effect scenarios.
However, one of the primary contributors to the said
causal events emanated from a number of significant design changes initiated
by the Employer. This situation was further complicated as a direct result
of the manner in which the consortium members’ workscopes had been
interfaced. As a result, and in the first instance, a number of claims
for time extensions and associated and other additional costs, loss and
expense claims were raised collectively by the Consortium against the
Employer. Many of the claims for time and money were successfully negotiated
and settled with the Employer. Nevertheless, our Client was subsequently
presented with extensive residual claims from the Consortium member responsible
for the manufacturing, supply, assembly, installation and commissioning
and testing of Waste Heat Boilers and associated works. Our Client had
tried but failed to reach a mutually agreeable settlement on all of these
residual claims.
CONSULTANCY SERVICES - Claims Management (Defence)
As a consequence of that situation, we were brought in by our Client to determine
which of these residual claims had contractual or other valid grounds and thereafter
evaluate the quantum, as appropriate. We undertook an initial review of all
relevant contract documents and correspondence in our client‘s UK offices
correspondence in order to establish the admissible basis of each claim from
the Consortium member, related to the design changes caused by the Employer
and those allegedly caused by our Client.
Our findings concluded that the Consortium member had
provided neither sufficient factual evidence in respect of the cause
and effect link of the alleged design changes, nor a consequent contractual
basis for each of its claims. We therefore requested the Consortium Partner
to provide further and better particulars in relation to compliance requirements
in accordance with contractual notice provisions appertaining to all
(caused by the Employer and / or our Client), alleged design changes,
delays, disruptions, contract variation orders together with the details
of all relevant correspondence. Among other items, the Consortium member
was requested to provide comprehensive details on take off quantities,
method of measurement, records of all discipline man-hours, constructional
plant and equipment, materials and the precise location of the alleged
design change, contract variation or design development item and its
alleged consequences related to the aforementioned resources.
Further details of the Consortium member’s sub-contracts
and supply contracts, including their details of all alleged design changes
(additions, amendments and omissions), with resultant impacts on their
work programmes and associated costs were also requested. Additionally,
a fully detailed final account from the Consortium member was also requested
to cross check the bases of their claims.
Despite our requests, the Consortium Partner was only
able to provide partial information which proved to be inadequate in
terms of demonstrating liability on the part of our Client. As a consequence
of this, we were able to satisfy the Consortium member that there was
no proven liability for any alleged design changes on the part of our
Client. The entire set of residual claims was successfully rebutted by
us and thereupon the Consortium member withdrew its claims and settled
the final account with our Client accordingly without serious damage
to the business relationship between the parties. |