Case Studies > National
Heavy Rail Link (High Speed)
Germany
A new 200km heavy rail link between two major cities
consisting of trackwork, switchgear, signaling, overhead power distribution,
tunneling, control systems, telecommunications, stations, various facilities
and substantial building and civil works. The Project was divided into
several geographic areas and systems with each package being put out
to tender by the local government public body ("the Employer")
responsible for all areas of the entire Project. Our client was one of
the contractors ("the Contractor"), awarded the contract for
all project locations specific to their scope of works.
KEY FEATURES
As a state organization for railways, the Employer procured the Works under
their own form of design and build contract, and awarded our client the Contract
Scope of Works on a fixed price, lump sum design & build basis. The scope
of works relative to the overhead power system, trackside signaling, telecommunications
and power distribution systems.
During the construction phase of the contract, a number
of serious delays occurred primarily resultant from client induced major
design changes, contract
variation orders and the complex series of interfaces with other executing
contractors. In recognition of these causal events, the Employer awarded several
extensions of time, numerous additional variation orders as well as a number
of substantial financial claims for compensation of additional costs and loss
and expense suffered by the Contractor. However, since that initial award,
further substantial design changes occasioned by the Employer arose causing
yet further delay to the Contract Completion Date. The Contractor subsequently
sought a further extension of time and reimbursement of prolongation and various
other additional costs.
CONSULTANCY SERVICES-
Project Profit Optimization - Investigations and Recommendations
Lancaster House International Consulting were requested
to attend a meeting at the client's project office in conjunction with
our alliance partner, Roland Berger Strategy Consultants. We were immediately
requested to recommend a strategy for a rapid and effective recovery
for time and costs. Roland Berger were given the specific remit to identify
possible causes of losses attributable to reasons other than those which
could be identified with and recovered through the contract provisions.
In collaboration, we deployed our consultants with
rail industry experience and undertook a thorough review and analysis
of the contract documentation and subsequently, we conducted an appraisal
of our client's draft claims (in German). Our appraisal was formulated
in a manner which readily established the optimal overall recovery levels
vis-a-vis alternative strategies.
Lancaster House International Consulting worked in
close liaison with our client's project management group ascertaining
the detailed history and background of the project. Following submission
of our analysis and recommendations for a claims turnaround and increased
recovery strategy, additional recommendations were submitted for the
installation of a Proactive Management System for Risk Identification
and Minimization allied to a means of improving financial recovery of
additional costs, loss and expense items during the remaining contract
period. Our recommendations were duly adopted by our client which led
eventually to a turnaround in their commercial and contractual position
vis-a-vis the Employer and an ultimately successful commercial outcome. |