Case Studies > Heat
Recovery Steam Generator (HRSG) Power Plant
UK
A new power generation plant based upon heat steam recovery generator technology
where the boilers are placed downstream of the gas turbines, thereby utilizing
waste gas. The Employer contracted with a major power generation organization
which acted as a quasi-management or principal contractor and where the firm
with the boiler technology know-how acted as the principle subcontractor on
a turnkey basis.
KEY FEATURES
Our clients were the boiler technology know-how specialists
who normally acted in the capacity of design and supply, but on this
occasion, they were awarded the principle subcontract. The scope of works
formed the essence of the entire project plant scope and in turn the
majority of their works was subcontracted out to piping, steel fabricator,
mechanical, electrical, instrumentation and control suppliers and subcontractors,
building contractors, steel erectors and equipment installation firms.
Our client therefore held the majority of the entire Project Works under
its responsibility and control but retained only the overall design coordination,
partial boiler design and supply, as well as the overall commissioning
and testing within its own direct sphere of operations. Many of the subcontract
packages were let on a typical purchase order basis designed to address
supply only conditions. Our client had been awarded its contract following
a two stage tender procedure with the first stage on a selective competitive
basis and the second stage on a negotiated basis. During the negotiation
process, the originally tendered sum had become drastically reduced but
a contract was finally awarded on a fixed price, lump sum basis for a
design and build style scope of works package. Many of the subcontract
and supply purchase orders were on a measure and value or cost reimbursable
basis. In short there was little in the way of "back-to-back" contracts"
CONSULTANCY SERVICES
Several months into the Contract Time for Completion
but prior to procurement and delivery of goods, materials and equipment,
it was becoming clear to our client that neither its planned rate of
progress, nor its forecasted discounted cash flow were developing according
to contract. Nor were the budgets for the project coming in on target
and there were a number of problems in regard to multi-discipline interface
coordination, compatibility issues and compliace with standards. Our
client was beginning to forecast a commercial loss.
We were initially asked to conduct a review of the
Main Contract documentation and determine what possibilites there might
be for recovery of the loss and expense incurred from commencement of
the Contract to date and thereafter assist in the prevention of further
loss and expense. Detailed investigations showed that certain losses
had been sustained during the negotiation process and were inherently
latent in the nature and content of the tender and contract documentation.
The nature and extent of these losses were exacerbated through the subcontract
and purchase order documentation. In short, not only had the parties
underestimated the planning, organization and resource elements of the
project, but they had adopted an entirely unsuitable project procurement
route to meet the Employer's objectives. As a result, when the project
moved from the design phase into the procurement and then construction
phases, a myriad of technical, commercial and contractual difficulties
arose which jeopardized the entire integrity of the project.
We established early on in our brief that there were
various routes to a financial turnaround for our Client, both upstream
vis-a-vis- the principal contractor and downstream vis-a-vis several
subcontractors. Simultaneously, we agreed to act as Project Managment
Assistants and Construction Managers in order to get workable negotiated
subcontract and supply orders in place, proper additional resources deployed
and the means for commercial and contractual control of the Contract.
Through the development of better communication channels,
re- negotiated agreements, improved means of works costing, applying
proper measurement and valuation principles all in agreement with the
management contractor, as well as through the establishment of contractual
change orders, dayworks, unit rate re- negotiation, working rule and
fluctuations agreements, all in addition to contractual and extra-contractual
claims against the principal contractor, we were able to substantially
reassert our client's financial position upstream. This process was further
complicated by the number of counterclaims which were raised and had
to be settled. Certain heads of claim items could not be amicably resolved
and became the subject of dispute leading eventually to settlement through
arbitration.
Our other avenues of recovery for our client were downstream
with the subcontractors and suppliers through a combination of increased
productivity, improved rates of progress and the installation of better
quality materials and workmanship. As a result of our turnaround managment
approach, many subcontractors sought compensation through contractual
and non-contractual claims. We were subsequently asked by our client
to settle all their key subcontract final accounts and were particularly
successful in rebutting the vast majority of their assertions for increased
quantities, additional or increased rates, variations, dayworks and claims
for additional costs and loss and expense. At the same time, we established
successful counterclaims and as a result of all these actions, we created
a sufficient basis for our client to record profitable packages or work
where previously they were reporting substantial financial loss. We therefore
undertook a broad role from assistants to the PM on strategy and tactics,
turn around construction managers, commercial, contractual and claims
managers and final account quantity surveyors. Ultimately, we provided
initial assistance to the legal team that became involved in the arbitration
process and submitted our recommendations for out of court settlements
together with our project records and statements. Finally, we submitted
reports to senior management on the prevention of such situations arising
in future on estimating, resource planning and programming, tendering
procedures, which forms of contract to use to suit the project objectives
and on the principles of Lancaster House International Consulting's Best
Pracice Procedures for commercial and contractual management.
Our involvement in the Project over a period of more
than 2 years is believed to have saved our client several tens of millions
of Euros and led to a change in the manner in which all future projects
were tendered and contracted. |