Case Studies > Gas
Fired Power Station
Location Confidential
The development of a new gas fired power station comprising
all associated building and civil engineering works, mechanical, electrical,
operation, instrumentation and control systems, boilers, gas fired turbines,
power generation and power distribution systems up to connection to the
national grid. The contract was awarded by a power generation company
(the Employer) to a consortium (the Contractor) of which our Client was
consortium leader, responsible for the turnkey provision of all mechanical
and electrical systems, the turbines, power generation and distribution
and all instrumentation and control systems.
KEY FEATURES
The Employer awarded a contract to the consortium on a fixed-price, lump-sum,
turnkey basis, utilizing its own form of EPC contract amended to include the
commissioning, testing and trial run commercial operation prior to hand over.
Within a matter of a few weeks, the contract programme began to suffer significant
slippage due to numerous causes of design disruptions and delays. This became
a pattern which continued throughout the engineering, procurement, delivery
and construction phases, again, arising primarily out of major design changes
instructed by the Employer. The impacts of these instructions were further
aggravated by a series of complex interfaces with other contractors engaged
by the Employer on the project. Various claims were submitted by the consortium
to the Employer and most were successfully negotiated and compensated. Our
Client, however, was subsequently confronted with substantial claims from the
civil works consortium partner as a result of alleged design changes instigated
by our Client rather than the Employer.
CONSULTANCY SERVICES - Claims Management (Defence)
Our Client appointed Lancaster House International Consulting to undertake
an initial review of the claims received from their consortium partner with
a view to establishing the extent of responsibility and possible liability.
A team of four claims consultants experienced in gas
fired power station design were mobilized within a matter of days to
our Client’s offices overseas. They undertook a complete review
of the project design, from the tender inquiry stage through contract
negotiations and award to during the execution phase. They also perused
all contract documentation, inclusive progress and financial analysis
reports, correspondence between the consortium members themselves as
well as with the Employer, claims submitted by the consortium to the
Employer and the results of those submissions.
Lancaster House International Consulting initially
found that once again, here was an example of a consortium partner who
had failed to provide a reasonable level of claim bases, neither in terms
of the extent and quality of documentary evidence, nor relation to the
contractual provisions, nor demonstrative clarity in the factual and
contractual argumentation, nor linkage between cause and effect,. Not
even sufficient basis and transparency was shown in the financial calculations
of damages suffered. In short, there was little to nothing in the way
of proper substantiation of its claims commercially and contractually.
In addition, our experts were also able to argue with conviction that
there were technical flaws in the consortium partner’s contentions.
Accordingly, we rebutted the submissions on demonstrable
grounds as initially made and then requested full substantiation of the
various statements of claim, inclusive further and better particulars
on maters of fact and record regarding events alleged to have caused
either disruption or delay or both; more detailed evaluations substantiation
of the alleged impacts upon the contract programme, greater clarity on
the manner and method of financial calculations, as well as details of
compliance with contractual notice provisions.
Without such further and better particulars we were
satisfied that an accurate review of the claims received could not be
undertaken which while it made the job of rebuttal quite simple, was
not conducive to the avoidance of a dispute that was not in the interest
of either party.
Subsequently, we received some of the further
and better particulars we had requested in support of its claims. The
extent and quality was insufficient for the purpose of having a proper
set of entire professionally presented claims documents, but it did
prove adequate in the circumstances to explain to the consortium partner
that they were not entitled under the terms of their agreement to allege
that the cited design changes were the liability of our client, even
in circumstances where our Client had initiated them, per se, or the
changes had passed via them emanating from either the Employer or another
consortium member. With the exception of the agreement of specific
minor variations to the works, the consortium member’s claims
were withdrawn in entirety and a costly dispute avoided. |