Case Studies > Aluminium
Plant
Location Confidential
Upgrading of an existing aluminium plant in sub Asia,
including the basic design, engineering, procurement and supply of key
equipment, the supervision of the civil works and erection. The contract
was awarded by a government agency responsible for industrial projects
(the Employer) to a consortium (the Contractor) of which our client was
one of the consortium members responsible for the basic design, procurement,
and supply of key equipment.
KEY FEATURES
The contract was awarded on a fixed price, lump sump, turnkey basis using the
Employer`s own form of design and build contract. Almost from the date of coming
into force, the project was subject to numerous causes of disruption, delay
and additional costs and expenses which continued to occur on a regular basis
during the various phases of basic design, engineering, materials procurement,
transport and erection. The collective result was both a serious delay to the
contract period of completion and most of the budgets set within the original
contract price being considerably exceeded. The most significant delays were
caused in essence by the Employer and the consortium partner responsible for
the execution of the civil works.
Our Client considered it was entitled to several extensions
of time and financial reimbursement arising from a loss of productivity,
contract period prolongation and other events caused by the Employer
and / or the consortium partner. Both the Employer and the consortium
partner contended that the delays were (in part at least) the cause or
responsibility of our Client.
CONSULTANCY SERVICES - Claims Management (Prosecution
/ Defence)
Lancaster House International Consulting were requested by our Client to undertake
a detailed contract review and analysis of the claims submitted by them against
the Employer and consortium partner together with the respective counterclaims.
The primary objective was to clearly demonstrate that the project delays were
caused principally by the consortium partner and / or the Employer in a manner
and to such extent that either the Contractor was entitled to an extension
of time equivalent to the total duration of demonstrable critical delay or
that any period of critical delay within the responsibility of the Contractor
could not be held to be our Client’s liability. The secondary objective
was to successfully defend any residual counterclaim position from either of
the two other parties. Achieving the primary objective would alleviate our
Client from the liability (share) of liquidated and ascertained damages for
delay, while at the same time it would assert their contractual entitlement
to the reimbursement of additional costs and expenses incurred through prolongation,
disruption, delay and other causes.
Through forensic research and carefully detailed and
presented analyses, we provided further and better particulars and thereby
demonstrated to the satisfaction of the other parties that all the critical
delays were their liability, individually and collectively. On behalf
of our Client, we subsequently secured the Engineer’s award of
an extension of time to the period for completion sufficient to alleviate
the Contractor from any liability for L & A damages. This position
alone alleviated a potential liability of tens of millions of US$. At
the time of writing, our Client’s prolongation costs (also in tens
of millions of US$), resulting from the awarded extension of time as
well as disruption loss and expense costs together with other minor issues
remain to be negotiated.
Finally, we were successful in rebutting in entirety
over 80% of the counterclaims received from the consortium partner and
the Employer. Negotiations with both parties currently continue in regard
to the remaining 20%. Irrespective of the items yet to be settled, our
Clients were extremely satisfied with the complete financial turnaround
that we were able to assist them with. |